Calculation of Pieces Per Hour from Cycle Time

Converting the cycle time to pieces per hour is a most used term in industrial engineering. To do it need the following parameters.
Average Cycle Time of The Process
Factory allowance percentage

Piece Per Hour,Cycle Time,Garments IE,IE

The formula for converting cycle time to piece is below.
Hourly Piece= [(3600/ (Average Cycle Time of The Process+ 20% Allowance)]

(Note: 1 hour = 3600 seconds Allowance may vary factory to factory)


Let say,
Average cycle time of the process = 25 seconds and
Factory allowance percentage = 20% then

Piece Per Hour = 3600/ (25+25 × 20%) = 3600/30 = 120 Pieces